Standard SAP flow for consumption is (For component which are WM managed)
1) Create Production order
2) Release production order, Perform material staging
3) System creates Transport Request (TR)
4) Create Transfer order against the TR
5) Transfer the stock to the PSA / Control cycle bin by confirming the transfer order
6) During consumption system will consume the stock from the control cycle bin, if stock is not there the it will create negative quant in storage type 914(as per movement type 261 setting)
7) if negative Quant exist then you have to manully transfer the stock using SAP T-Code LT01 to the bin
Now i don't think by just changing the material master (Not sure which field are you talking in Material master) you will be able to achieve the required result