Hi Pete,

 

Thanks for the quick response.

 

Actually i read the provided link prior to posting this question.

 

Based on that my doubt was:

  1. On which case we should use Restart in cycle after last date and
  2. On which case we should use Restart in cycle after next date
  3. After rescheduling, I hope should run IP30 for all those maintenance plans to generate updated maintenance order/ schedule.

 